With the nice weather we’ve been having, Bhh Partners took the opportunity to take a few exterior photos of the new Perham High School construction progress! We are nearing the point where items are being checked off a list, so we are excited to start seeing the light at the end of the proverbial tunnel.
Here is what we can expect moving forward:
- Final Indoor Concrete Floor Slab Pour – Late March
- Start Sidewalks, Curbs, & Parking Lot – Mid-April
- Gym Equipment & Floor Installed – End of May
- Start Remodel Work in PWMS – End of May
- Building Exterior Complete – Mid-June
- Landscaping & Irrigation – June – July
- Construction Completed & Move-in – August